Achievements of TREDA during 2007-08 to 2012-13 [ Up to March- 2013 ]

Remote Village Electrification Programme[ Electrification of 16 villages in South Tripura District]

  •     Name of the System- Solar Home Lighting System,M-V
  •     Nos of familly covered- 637nos
  •     Name of the System Installed & Commissioned- Solar PV Power Plant[10kwp ,3nos]

Remote Village Electrification Programme[ Electrification of 29 villages and 341nos hamlets in Tripura]

  •     Name of the System- Solar Home Lighting System,M-V
  •     Nos of familly covered- 18000nos
  •     Name of the System Installed & Commissioned- Solar Street Lighting System[180nos]

Remote Village Electrification Programme[ Electrification of 205 nos hamlets in Tripura]

  •     Name of the System- Solar Home Lighting System,M-II
  •     Nos of familly covered- 6950nos

Remote Village Electrification Programme[ Electrification of 251 nos hamlets in Tripura]

  •     Name of the System- Solar Home Lighting System,M-II
  •     Nos of familly will be cover - 7278nos
  •     Total System Installed & Commissioned-7136nos

BRGF Programme under Dhalai District

  •     Name of the System- Solar Home Lighting System,M-V
  •     Nos of SHLS installed & commissioned- 500nos

Solar Lantern Programme[ 15500nos Solar Lantern , M-IIA]

  •     Name of the System - Solar Lantern,M-IIA
  •     Total System Installed & Commissioned-15,000nos in Rural Areas & 500nos among BPL Girl Child, free of cost, who studing in class-IX-XII

Solar Lantern Programme[ 20,000nos Solar Lantern , M-IIA]

  •     Name of the System - Solar Lantern,M-IIA
  •     Total System Installed & Commissioned-20,000 nos in Nagar Panchayat & AMC Area

SPV Power Plant

  •     Name of the System- Solar Photovoltaic Power Plant [1Kwp-12nos,2Kwp-2nos,3 Kwp-3nos.10Kwp-1no]
  •     Total System Installed & Commissioned-
  1.     Block Office- 10nos [ 1kwp]
  2.     DMs Office-2nos[2kwp]
  3.     Neermahal-2nos[ 3 kwp]
  4.     Hon'ble CM Office-1nos[3 kwp]
  5.     Laxman para SB School,Killa Block- 1no [ 1 kwp ]
  6.     Rajya Sainik Guest House- 1no [ 1 kwp]
  7.     State Level Energy Education park- 1no [ 10 kwp]

Solar Water Heating System[ 61,500 LPD] 

  •     Installed & Commissioned- 61,500 LPD

Solar Street Lighting System [SLS][ 1300nos SLS]

  •     Name of the System - Solar Street Lighting System

Wind Solar Hybrid Power Plant-2kwp

  •     Name of the System - Solar Power Plant-1 kwp + Wind Power-1kwp
  •     Total System Installed & Commissioned-2Kwp Wind Solar Hybrid Plant installed & commissioned at the roof top of TREDA office building
  •     Total Power generated from this System-1364unit upto April-2013